Search by Keyword(s)

Table of Contents
Understanding PredecessorsUnderstanding Dependency TypesUnderstanding Task ConstraintsUnderstanding Default Constraint PreferencesWorkfront Predecessors & Task Constraints
Understanding Predecessors
Predecessors set the order of tasks
- Chains of predecessors set the length of the project.
- Allows groups of tasks to shift automatically.
Predecessors in Action: Standard
Sets the order in which tasks are to be done.
- Develop Initial Invite Copy must finish before Approve Initial Invite Copy can start.

Predecessors in Action: Lag Time
Add gap days between tasks.
- Present Design Concepts must start 5 days after Create Design Concepts is finished.

Lag Time Uses Cases
- Create additional buffer time between tasks.
- Account for SME/Partner approval.
- Reschedule late tasks to bring them current.
Predecessors in Action: Negative Lag Time
Sets a task to run before its predecessor.
- Send Attendee/Staff Email must start 3 days before Day of Tradeshow (Task 1) is finished.

Negative Lag Time use case:
- Quickly create a successor relationship to a fixed date.
- Ad-hoc tasks tied directly before the event date.
Predecessors in Action: Multiple Predecessors
Set up multiple tasks to lead up to a single activity.
- Approve Final Copy (Content) and Approve Design Concepts must finish days before Edit Design Concepts can start.

Multiple Predecessor use cases:
- Easier to delete sections without affecting the entire project.
- Deleting booth tasks or other event materials.
- Set tasks to run parallel to each other.
- Content & design.
Understanding Dependency Types
Determines when a task should start or finish with relation to other tasks.
-
Dependency Types:
- Finish-Start (fs)
- Finish-Finish (ff)
Finish-Start (fs)
The default dependency type.


Finish-Finish (ff)
Use to set tasks to run in parallel.
- Even if tasks have different duration days, they will finish at the same time.

Understanding Task Constraints
Task Constraints
- Must Finish On
- Must Start On
- As Soon As Possible
- As Late As Possible
Constraint: Must Finish On
- Assigns a due date regardless of PTO, weekends and holidays.
- Also prevents the task from shifting with the rest of the project.
- Including if someone adds PTO after the fact.
Two ways to set Must Finish On:
- Set task constraint in the Task Constraint column.
- Manually enter the due date.

The start date is determined by the task’s duration days.
Constraint: Must Start On
- Assigns a start date regardless of PTO, weekends and holidays.
- Also prevents the task from shifting with the rest of the project.
- Including if someone adds PTO after the fact.
Two ways to set Must Start On:
- Set task constraint in the Task Constraint column.
- Manually enter the start date.
The due date is determined by the task’s duration days.
Constraint: As Soon As Possible (ASAP)
Default task constraint.
- Tasks will shift automatically based on weekends, holidays and PTO.
- Tasks will also shift based on rescheduled predecessor tasks.
As Soon As Possible (ASAP) in action:
Tasks without a predecessor will start at the Planned Start Date of the project.

As Soon As Possible (ASAP) in action:
Tasks will move adjacent to their successor task.

Constraint: As Late as Possible (ALAP)
Tasks will shift automatically based on weekends, holidays and PTO.
- Tasks will also shift based on rescheduled successor tasks.
As Late As Possible (ALAP) in action:
Tasks will move adjacent to their successor task.

As Late As Possible (ALAP) in action:
Tasks without a successor will finish at the Planned Completion Date of the project.

Understanding Default Constraint Preferences
Ever wondered why the system sets the As Late As Possible constraint for a new task?

Answer: Your project may be scheduled from Completion Date.

Click Edit to find out!

